Below is a quick update and summary of the CS Projects at TCP:
FSO-PVA: Pilot Complete, making final edits. Completion by end of July.
FSO-PI: In middle of Pilot. On target for end of July Completion.
JOD SOJT: Making final edits before pilot to start in July. Stand by for email with information requesting assistance in gathering pilot participants. Project is on target. LCDR Vryheid and I have spoken about long term tracking. LCDR Vryheid will reach out near completion of project to have a DA competency code developed for members to earn upon completion of the SOJT.
C-STAR (Sanitation): Making final edits before July pilot. Stand by for email with information regarding pilot and access to the pilot documents. LCDR Vryheid and I have determined the way ahead to make the training show up as a MT-B training for all CS. However, this cannot be completed until training is deployed to live LMS.
CS-A School Max Size Waiver: In routing at TCP. Will be sent to FC-T once signed. FC-T is aware the memo is coming and will sign ASAP.
Please let me know if you have any questions or concerns.
Very Respectfully,